Selasa, 7 Jun 2011

Building A Small House - 3rd Update



Progress as at 31/05/2011

Went back to Melaka a day before we off to Langkawi. About ten days after our last visit, the walls are about 50% complete. They were pacing their work quite well considering raining was quite often here in Melaka.

Shot taken from the front

Taken from back of the house

Below is the photo taken from the right side of the house. The window in this photo had been missed located. It is supposed to be placed at the centre of the wall. It was my mistake since I forgot to to give Edi the new drawings after we made few changes to the roof design. It is quite an easy task to relocate the window since the wall is only half way constructed.

Taken from right side

The followings are photos from inside the house. And also I post the building sketches vs the actual work done so far as at 31/05/2011 to give a better idea of what is being in progress.

Comparison 1
Dining and kitchen

This is where the dining and kitchen area would be
(window on right was before redo)

Comparison 2
Living area

Here is the living room. The door frame on the left is the main front door.

Comparison 3
Second bathroom, the one with yellow door

The bathroom

Will update again soon...

Tiada ulasan:

Catat Ulasan